15:58
USD 87.00
EUR 90.41
RUB 0.84

Capacity of 15 substations in villages of Chui region to be increased

Since the beginning of March, branches of district power networks of Bishkek, Chui and Talas regions have started annual scheduled repairs. Press service of Severelectro OJSC reported.

In order to improve reliability of power supply to consumers, trees will be trimmed along 46 kilometers of transmission lines in Alamedin district.

More than 71.1 kilometers of overhead power lines will be reconstructed in Baytik, Kashka-Suu, Leninskoye, Vinogradnoye, Vasilyevka, Oktyabrskoye, Mayevka, Prigorodnoye, Vostok, Alamudun villages using self-supporting insulated wires.

The wires are lightweight, resistant to snow build-up, reliable in case of intense icing and wind.

In addition, power engineers will install three additional transformer substations in Lebedinovka, Leninskoye and Chon-Tash villages, increase the capacity of 15 overloaded transformer substations in Vasilyevka, Konstantinovka, Oktyabrskoye, Leninskoye, Lebedinovka, Vostok, Prigorodnoye, and Mayevka villages.

Popular