By the beginning of the heating season, Severelectro OJSC will install 43 additional complete transformer substations. The press service of the company reported.
Passage of the autumn-winter maximum is characterized by a high load on distribution networks. In some areas of the electricity grid, low-voltage networks and transformer substations operate at over a hundred percent in winter, which leads to equipment damage and an increase in the number of breakdowns.
In order to unload the most loaded substations, Severelectro will install 4 transformer substations at its own expense in Bishkek, 24 — in Chui region, and 15 — in Talas.
The land allocation procedure has been completed. As of July 1, at least 14 transformer substations of 6 / 10-0.4 kV have already been installed.