Cascade of Alamudun HPPs to be repaired

Chakan GES JSC plans to make major and medium repairs of hydroelectric units of the cascade of Alamudun hydropower plants. The state procurement portal says.

Mechanical cleaning and repair of the pipeline, installation of a compensator of the hydro turbine at Lebedinovskaya HPP are also planned.

In total, it is planned to spend almost 10.5 million soms on the repairs.