Repair of Bishkek HPP requires over $ 1.2 million

Electric Stations OJSC will spend $ 1.2 million on the repair of the cable track of the Bishkek Heating and Power Plant. The state procurement portal says.

It is planned to reconstruct the cable track at the shore pumping stations with the installation of new switching equipment at the heating plant.

Electric Stations Company is ready to pay 81,849.6 million soms to a contractor within 30 working days from the moment of signing an act of completed works.