Repair of Tash-Kumyr hydropower station to cost 102 million soms, the chief engineer of the hydroelectric power plant Taalaibek Bektenov said during a press tour to energy facilities in Jalal-Abad region.
According to him, the funds will be spent on installation, electrical and finishing work.
At one time, due to lack of financing, finishing works at the hydroelectric station were never completed. In 2017, the task is to complete them before October.
Taalaibek Bektenov
As he noted, the company «Narynhydroenergostroy», which won a tender for contract work, produces granite floors, wall cladding and other finishing works.
In addition, according to the chief engineer, in 2017, It is planned to replace the excitation system of one of the hydro-power plant units at Tash-Kumyr hydropower plant. «Some equipment is more than 30 years old, and the time of its modernization has already come," he said.
According to Taalaibek Bektenov, the tender for replacement of the equipment was won by the Russian company.