Bishkek's heating networks are 68.6 percent worn out
Heating networks in Kyrgyzstan's capital are 68.6 percent worn out, Yuri Dmitrushchenko, deputy chief engineer for in-building systems at the municipal enterprise Bishkekteploset, said on Birinchi Radio.
According to him, heating pipes have a service life of 25 years.
"Some networks in Bishkek have been in service for 40 or even 50 years. But we are working to address this. For example, the wear rate previously exceeded 70 percent, but has now fallen to 68.6 percent. We replace pipes depending on available funding,” Dmitrushchenko said.
He provided figures for the work carried out in recent years: 3,365 meters of pipelines were replaced in 2022, 3,666 meters in 2023, 3,770 meters in 2024 and 4,551 meters in 2025. In 2026, 3,840 meters have been replaced so far, against a target of around 5,000 meters for the year.
"We use new technologies that do not require extensive excavation work,” he added.
Dmitrushchenko said the municipal enterprise maintains 481 kilometers of pipelines, 22 pumping stations and 2,482 individual heating units. It also provides technical maintenance for 2,070 residential buildings.
He noted that the city was undergoing decentralization of its heating system, with end users switching to boiler houses serving specific areas.
"This year, these changes will affect microdistrict No. 10, Gorodok Energetikov, Gorodok Stroiteley and Uchkun microdistrict,” he said.
The municipal enterprise representative assured residents that Bishkekteploset was ready for the upcoming heating season.
The start date for the heating season has not yet been announced.