High-voltage networks of Kyrgyzstan being prepared for winter loads

Commissions check the readiness of enterprises of high-voltage electrical networks — branches of National Electric Network of Kyrgyzstan OJSC — for the coming autumn-winter period. The press service of the company reported.

Commissions’ work will end on October 6. According to its results, the acts of readiness of enterprises of high-voltage electrical networks for autumn-winter period will be drawn up and measures to eliminate shortcomings will be developed.

Currently, a complete overhaul of 101.8 kilometers of 110 kV overhead lines has been completed. Before the start of the heating season, overhaul of four transformers with a total capacity of 91 MVA will be completed.

The planned activities of the company in preparation for the heating period are carried out according to the approved plan, there is no delay.