19:13
USD 87.45
EUR 90.05
RUB 0.85

Power engineers to install 41 transformer substations for 15.5 mln soms

Before the winter season, Severelectro plans to install 41 additional transformer substations with a voltage of 6/10-0.4 kV at its own expense. Press service of the distribution company reported.

It is specified, the new equipment will unload the most loaded substations. 15.5 million soms are provided for this purpose.

Four substations will be installed in Bishkek, 23 — Chui region and 14 — in Talas region.

It is noted that as of August 1, 2017, 32 additional transformer substations of 6 /10-0.4 kV have already been installed: in Bishkek — 1, in Chui region — 17 and in Talas region — 14.

Popular