Repair of Bishkek HPP requires over $ 1.2 million

11:57, 05 September 2018, Bishkek - 24.kg news agency
Julia KOSTENKO

Electric Stations OJSC will spend $ 1.2 million on the repair of the cable track of the Bishkek Heating and Power Plant. The state procurement portal says.

It is planned to reconstruct the cable track at the shore pumping stations with the installation of new switching equipment at the heating plant.

Electric Stations Company is ready to pay 81,849.6 million soms to a contractor within 30 working days from the moment of signing an act of completed works.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18