Preparation of Bishkek HPP for winter to finish in September

10:47, 10 August 2018, Bishkek - 24.kg news agency
Julia KOSTENKO

The press service of Electric Stations JSC told about the preparation of the Bishkek Heating and Power Plant for the upcoming heating season.

A contract for the supply of local coal was signed with the leader of the coal mining partnership — Kyrgyzkomur state enterprise. Actually, 65.144 tons of Kavak coal have been delivered.

Process of concluding a contract with Passvet Company for the supply of imported fuel in the amount of 400,000 tons is underway. A tender for the supply of 50,000 tons of Kyrgyz long-flaming coal was announced.

At least 12 boilers and heating networks will be repaired at the Bishkek HPP. Repair of two out of seven planned turbo-units was completed. The remaining turbines will be removed out of service on schedule. They will be repaired before the start of the heating season.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18