11.2 million soms to be spent on heat insulation of Bishkek HPP impulse lines

11:06, 04 May 2018, Bishkek - 24.kg news agency
Julia KOSTENKO

At least 11.2 million soms will be spent on heat insulation of the impulse lines of the Bishkek Heating and Power Plant. Electric Stations JSC announced a tender for the works.

Some impulse tubes are planned to be replaced. The main works are aimed at insulation of the lines of the boiler units of Bishkek HPP.

During the January breakdown at the power plant, impulse tubes of devices in the boiler shop began to freeze. The personnel warmed them to prevent the technological pipelines from freezing, which are necessary for ignition of standby and disconnected boilers.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18