Former director of Bishkek HPP tells about true causes of January breakdown

11:04, 15 March 2018, Bishkek - 24.kg news agency
Julia KOSTENKO

The search for the true cause of the breakdown at the Bishkek Heating and Power Plant will lead to a modernization project. The former director of Bishkek HPP Omurkul uulu Nurlan told today at a press conference.

According to him, he did not receive a dismissal order. However, he was no longer let to his workplace. No one came to the contact. «The investigation was biased. They talk about the lack of chemically demineralized water and the uncoordinated actions of the staff. If we talk about the true causes, they will lead to the modernization of the HPP,» Omurkul uulu Nurlan said.

He confirmed the information that expensive tools were bought at the expense of the Chinese loan. For example, the pliers were bought for $ 640.

«There was an oral order of the leadership not to cast a shadow on modernization. I cannot voice names, because it is not recorded in writing. Overestimated prices was a known fact. The Accounting Chamber noted this in its audit. There were witnesses, but I do not know how they will behave and whether they will confirm it. The real cause of the breakdown is a lack of a chemical plant. This has already been acknowledged, although at first they blamed the pump and personnel,» said Omurkul uulu Nurlan.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18