$175 million to be allocated for 3rd phase of Toktogul HPP rehabilitation

15:07, 03 July 2017, Bishkek - 24.kg news agency
Nargiza TOKOEVA

$ 175 million will be allocated for the third (final) phase of rehabilitation of Toktogul hydropower plant. Press service of Electric Stations JSC reported.

According to it, Almazbek Atambayev signed a law on the ratification of agreement on the financing between Kyrgyzstan and the Asian Development Bank.

110 out of $ 175 million will be allocated by the Asian Development Bank (60 million — a loan, 50 million — a grant) for a period of 40 years with an 8-year grace period at 1 percent per annum. $ 40 million will be allocated by the Eurasian Development Bank at 1 percent per annum for a period of 20 years and with 8 years of grace period. $ 25 million is the share of Kyrgyzstan.

«The first phase of the rehabilitation of HPP included replacement of 500 kV cable lines, generator switches, repair and restoration of other electromechanical equipment of the station. The second phase is the replacement of the second and fourth hydrounits. And the third includes restoration and replacement of the remaining first and third hydrounits," the ministry’s press service said.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18