Large substation, energizing several districts of Chui region, upgraded

09:38, 27 April 2017, Bishkek - 24.kg news agency
Julia KOSTENKO

A large 220 kV substation Kara-Balta, which energizes Panfilov, Moscow, Jaiyl and Sokuluk districts of Chui region of Kyrgyzstan as well as Junda oil refinery, was modernized.

The substation was put into operation in 1976 with a single autotransformer. Under ADB project, morally and physically obsolete oil switches were replaced with modern ones. New sealed voltage transformers and current transformers were installed.

Currently, a lightning protection wire with fiber-optic cable was laid from the substation Kara-Balta to Glavnaya substation and further to Chuyskaya substation with a total length of 150.4 kilometers, as well as from Kara-Balta substation to Frunzenskaya substation with the length of 63 kilometers.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18