Bishkek HPP to burn more coal

10:41, 25 March 2017, Bishkek - 24.kg news agency
Julia KOSTENKO

Bishkek’s Heating and Power Plant will burn more coal after its modernization, the State Committee of Industry, Energy and Subsoil Use informed in the report on the results of the heating season.

Kyrgyzstan's power engineers are already preparing a draft resolution for preparation for the heating season-2017/2018. In total in the republic it is necessary to procure 2,315,716 tons of coal.

For the Bishkek HPP it is planned to procure 1 million tons of coal, including 550,000 tons of local coal. Supplies of coal from the Kavak basin will increase by 165,000 tons due to an increase in demand for Kyrgyz coal after the completion of the reconstruction of the Bishkek HPP.

Last year, according to the government’s decree, the heating plant needed to procure 950,000 tons of coal, including 450,000 tons of local coal.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18