Major modernization underway at Uch-Kurgan HPP
Major modernization work is underway at Uch-Kurgan Hydropower Plant (HPP), which will upgrade the station’s equipment and increase its installed capacity. The Ministry of Energy of Kyrgyzstan reported.
According to the ministry, work to replace generating unit No. 2 has been completed. Work on the replacement of generating unit No. 1, as well as upgrades to the plant’s production infrastructure, continues.
The full modernization of the plant is scheduled to be completed by the end of 2026. Once all work is completed, the installed capacity of the Uch-Kurgan HPP will increase from 198 to 216 megawatts.
The plant’s reconstruction began in 2024. As part of the project, generating units No. 4, 3 and 2 have already been fully replaced, increasing the plant’s capacity by 27 megawatts.
The Uch-Kurgan HPP is located in Jalal-Abad region on Naryn River. The plant was commissioned in 1961–1962. After more than 60 years of operation, the current reconstruction is the first major upgrade of the station’s main equipment.