Bishkek heating decentralization: 187.8 million soms allocated for first phase

11:50, 29 September 2026, Bishkek - 24.kg news agency
Grigory PRUTKOV

A total of 187.8 million soms has been allocated for the first phase of a project to decentralize the heating system in Bishkek, the city authorities said.

The project will cover the 10th microdistrict, Gorodok Stroiteley and Gorodok Energetikov. According to the municipality, the three areas have a total of 7,346 heating consumers.

Two local gas-fired boiler houses with a combined capacity of 52 megawatts are being built to serve residents. They are about 90 percent complete and are scheduled to be commissioned before the start of the heating season.

The City Hall said the areas were selected because of their distance from the centralized heating system. According to municipal estimates, the project will help reduce heat losses and network maintenance costs.

At the same time, Bishkek’s Heating and Power Plant will not be completely phased out. It will continue to supply the city with heat and electricity.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18