About 9 billion soms planned to be spent on fuel for Bishkek HPP
To get through the 2026–2027 heating season, the Bishkek Heating and Power Plant (HPP) needs to stockpile 1.52 million tonnes of coal and 1,000 tonnes of fuel oil, as well as use 75.2 million cubic meters of gas. The City Hall informed 24.kg news agency.

City authorities stated that imported D-grade coal will account for 200,000 tonnes of the total solid fuel volume.
In total, fuel expenditures for the Bishkek HPP this year are projected at approximately 9 billion soms.
Meanwhile, 368,000 tonnes of coal have already been delivered to the facility. This exceeds the volume originally planned for stockpiling by October 1 (300,000 tons), the City Hall noted. Procurement will continue until April 2027.
The municipality emphasized that there are currently no grounds to anticipate a fuel shortage during the heating season.