155 tons of toxic substances to be neutralized at Crystal plant in Tash-Kumyr
Up to 155 tons of hazardous chemical substances remaining at the former Crystal plant in Tash-Kumyr for more than 15 years are to be neutralized.
According to the Ministry of Emergency Situations, specialists are currently preparing the site for the work. The project stages and safety measures were presented to residents at a meeting on September 15.
The plant was built in 1989 to produce polycrystalline silicon. It was shut down in 2010 without being properly mothballed, and the production lines were not cleared of toxic and explosive substances.
First, specialists will stabilize the pressure in the process vessels, open them under controlled conditions and neutralize the gases released. The chemicals will then be removed from the tanks and neutralized through alkaline hydrolysis.
The ministry said the environmental situation would be monitored at every stage of the work.
«For the residents of Tash-Kumyr, it is important to understand not only the ultimate goal of the project but also how safety will be ensured directly during the work. That is why monitoring must accompany every stage,» Kylychbek Apiev, deputy director of the ministry’s department responsible for tailings management, said.
In May 2024, the Cabinet of Ministers instructed the Ministry of Emergency Situations to eliminate and dispose of hazardous substances at the Crystal site. At the time, it was reported that about 80 tons of hazardous chemicals had been discovered.