Three of four hydropower units repaired at Kurpsai HPP
Three hydropower units — No. 2, 3 and 5 — have been repaired at the Kurpsai hydropower plant (HPP). The work is being carried out as part of preparations for the 2026–2027 autumn-winter period.
A major overhaul of hydropower unit No. 1 is scheduled for the third quarter.
Repairs of four power transformers have been also completed at the HPP.

Maintenance and repair of electrical equipment, including 6 kV switchgear, are ongoing.
Scheduled work is also being carried out on auxiliary equipment, hydraulic structures, production buildings and the plant’s engineering systems.
The Kurpsai HPP is located on Naryn River and is part of the Toktogul cascade of hydropower plants.