Waste processing and energy generation plant to be launched in Osh in 2027
A waste processing and energy generation plant is under construction in Osh. It will be the second large facility of its kind in Kyrgyzstan.
According to the Osh City Hall, construction of the first floor has been completed, and work on the second is underway. Around 200 construction workers are working on the site.
The plant is being built by the Chinese company Junxin Huanbao KG Invest. The project cost is 8,312 billion soms.
Once fully operational, the plant will be able to process over 800 tons of waste per day, or up to 310,000 tons per year. The processed waste is planned to generate up to 30 megawatts of electricity.
The plant is scheduled to be commissioned in late 2027. According to the project terms, the plant will become the property of the Osh City Hall after 35 years.