Overhaul of 36 transformers completed in Issyk-Ata district

10:22, 17 September 2025, Bishkek - 24.kg news agency
Aibek SULTANOV

Energy specialists of Chui Electric Grid Enterprise have completed the overhaul of 36 transformers in Issyk-Ata district. The company’s press service reported.

According to the statement, the following works were also carried out:

  • Major repairs of 5 kilometers of overhead power lines;
  • Installation of 6 kilometers of self-supporting insulated wire lines;
  • Maintenance of 183 transformers and 450 kilometers of overhead lines;
  • Replacement of 2 transformers with higher-capacity units as part of capital construction.

Planned repair works as part of preparations for the winter heating season have been completed by 80 percent.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18