Three substations built and commissioned in Naryn region

09:58, 17 June 2025, Bishkek - 24.kg news agency
Aibek SULTANOV

Three high-voltage substations have been built and commissioned in Naryn region of Kyrgyzstan. The Ministry of Energy reported.

The substations were built to provide electricity for the construction of China-Kyrgyzstan-Uzbekistan railway:

  • Korgon-Tash substation with a capacity of 10 megawatts 110/35 kilovolts, located in At-Bashi district. It is connected to the 110 kilovolt overhead line Ala-Too — Torugart.
  • Kosh-Dobo substation with a capacity of 20 megawatts 110/35 kilovolts, built in Kosh-Dobo village, Ak-Tala district. It is connected to the 110 kilovolt overhead line Ugut — Ala-Buga.
  • Chet-Bulak 110/35 kilovolt substation with a capacity of 16 megawatts was built in Chet-Bulak village in Toguz-Toro district. It is connected to the 110 kilovolt overhead line Zhetigen — Ala-Buga.

This project was completed ahead of schedule and put into operation based on an agreement between NES Kyrgyzstan JSC and Chinese-Kyrgyz Railway Construction Company. Naryn Electric Grid Company provided the substation with the necessary capacity for the construction of the railway.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18