Hot water supply in Bishkek apartments to resume on June 1

13:27, 31 May 2025, Bishkek - 24.kg news agency
Saliya KHUROVA

The supply of hot water to Bishkek’s heating networks will begin on June 1. The press service of the City Hall reported.

Bishkek Heating and Power Plant municipal enterprise (Bishkek HPP) is operating as usual and will start filling and supplying hot water on May 31.

Currently, two boiler units and two turbo units with cross connections are in operation. Twelve boiler units and two turbo generators are under repair.

The average electrical capacity is 51 megawatts, and the remaining fuel in the Bishkek HPP warehouse as of May 26 is 262,160 tons of coal.

Hot water supply in the city was stopped on April 21 for preventive maintenance and repair work.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18