Unit No. 3 undergoing reconstruction at Uch-Kurgan HPP

17:23, 09 April 2025, Bishkek - 24.kg news agency
Artem SUVOROV

Major reconstruction works are ongoing at Unit No. 3 of the Uch-Kurgan Hydropower Plant, a branch of Electric Power Stations OJSC. The press service of the Ministry of Energy of Kyrgyzstan reported.

As reported, 91 percent of the dismantling work for Unit No. 3 has already been completed.

Currently, the following key reconstruction stages are underway:

  • Dismantling of the runner blades,
  • Dismantling of the runner chamber,
  • Installation of pipelines for the technical water supply system,
  • Assembly of the stator core,
  • Setup of the control system at the new central control panel.

The updated Unit No. 3 is scheduled to be commissioned in November 2025. Once reconstruction is complete, its capacity will reach 54 megawatts — an increase of 9 megawatts compared to its pre-upgrade output.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18