New substation and power transmission line built in Osh region

12:28, 11 December 2024, Bishkek - 24.kg news agency
Aibek SULTANOV

A new administrative building of Kara-Kuldzha power distribution zone, a 110/10 kilowatt substation Bulolu and a 10 kilovolt power transmission line Zhar-Bashy — Jekendi were put into operation in Osh region. The press service of the Ministry of Energy of Kyrgyzstan reported.

The new modern building of Kara-Kuldzha district power distribution zone was built to replace the dilapidated one, which was built back in 1965.

The commissioning of the 110/10 kilowatt substation in Bulolu village, Alai district, will provide the local population with a stable power supply.

Construction of the 10 kilovolt power transmission line Zhar-Bashy — Jekendi with a length of 22 kilometers improved the quality of power supply to 1,335 consumers in Jekendi village.

All facilities were built at the expense of NENK OJSC.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18