1.5 billion soms allocated for construction of Kambarata HPP-1

09:20, 01 July 2022, Bishkek - 24.kg news agency
Darya PODOLSKAYA

A loan in the amount of 1.5 billion soms was allocated from the republican budget for the construction of Kambarata HPP-1. The Cabinet of Ministers confirmed the information to 24.kg news agency.

The recipient of the loan is Electric Stations OJSC. Kambarata HPP-1 is the largest power facility of the entire cascade.

The project provides for the construction of a rockfill dam 256 meters high and the station itself with an installed capacity of 1,860 megawatts. An average long-term electricity generation at the Kambarata HPP-1 will be 5.6 billion kilowatt-hours with a total reservoir capacity of 5.4 billion cubic meters of water.

The construction period is from 8 to 10 years. Commissioning of the first hydroelectric unit of the HPP is planned in four years, if there is permanent financing.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18