Repairs at Toktogul HPS completed

13:04, 06 January 2017, Bishkek - 24.kg news agency
Julia KOSTENKO

Second hydroelectric unit at Toktogul hydro-electric power station is in service again, Chairman of the State Committee for Industry, Energy and Mining Duyshenbek Zilaliev said to 24.kg news agency.

 

According to him, the broken cable line is fixed today at 1.46 am. Yesterday it worked in a test mode.

 

Currently, the plant produces 200 MW. The station is operating in normal mode.

 

Recall, the accident happened on the night of December 16. Cable line, which broke down on December 23, 2015, damaged. It was planned to replace 28 m of cable. Its complete replacement will begin in spring.

 


CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18