Power engineers continue to eliminate consequences of Toktogul HPS breakdown
Repairs after Toktogul hydro power station breakdown continue, experts began insulation of a new cable. National Energy Holding informed 24.kg news agency.
It is noted that experts have started insulation of the cable line. The works will last two days. The new cable has been already laid, connected, and now engineers have to weld it.
Power engineers plan to launch the second hydraulic unit after January 10.
The damage occurred on 500 kV cable line, phase C, 15 meters below the coupling. It is planned to replace 28 meters of cable. It is in reserve. Complete replacement of the cable line will start in spring.
Recall, the breakdown happened on the night of December 16. Cable line, which broke down on December 23, 2015, was damaged. Currently, the second hydraulic unit is stopped.