For two months in the Boom gorge recorded 19 natural disasters, one of which claimed Kyrgyzstani. But power authorities only report about the services mobilized to clear the track from the stones. Everyone knows about the high likelihood of rock falls and mudslides, but no one recognizes, why mudflow-directing structures and barriers are not provided on the dangerous sections.
Inaction = crime
Last week, the Prime Minister Sooronbay Jeenbekov held a meeting on ensuring safe passage on the Boom gorge. He stated that from May 5 to August 3 there were 7 rockfalls and 12 mudslides at the track. Heads of ministries reported that there is specialized equipment and works patrol service of Interior Ministry.
According to the Minister of Transport and Road Zamirbek Aidarov, the Commission clarifies the causes of flooding of the road from the 136th to 140th km due to the rains. The audit will eliminate possible defect in the road structure.
Officials know that landslides will repeat soon. Minister of Emergency Situations Kubatbek Boronov said that in Boom gorge found 94 debris, 16 avalanchine and 2 landslide sections. Of these, 17 debris areas, 3 sections of collapse and one landslide pose a particular threat.
At the height of the tourist season the Main Department of the patrol police of the Ministry of Interior recommended not to travel due to rockfalls. But to stop the flow of cars rushing to the lake is impossible. As a result, another mass of mud covered a van, in which were 11 people. One passenger was killed. Isn\'t this a reason to hurl all effort into strengthening the dangerous areas and not wasting time on the investigation?
Finding guilty
Reconstruction of Bishkek - Naryn - Torugart highway will cost Kyrgyzstan $400 million, not including interest on loans. Plot from 2 to 272 km is financed by Export-Import Bank of China, having allocated $200 million.
At a meeting of government officials acknowledged that in some areas there are no mudflow-directing structures. When the road reconstruction project was prepared, the Ministry of Emergency Situations has given an opinion on the need for protection against rockfalls. \"In 2011 came the answer, everything is observed. Today, as a result of heavy rainfall, we see that the stones don\'t hold, so avalanches occur, - Minister of Emergency Situations Kubatbek Boronov said to 24.kg news agency. - An examination of roads Bishkek - Naryn - Torugart and Balykchy - Karakol - Enilchek identified 73 hazardous areas, a few mudflow dangerous areas found. Protective measures should be organized by the Ministry of Transport and roads, because barriers are installed not everywhere. On our side, there are rescue teams in Boom Gorge during the tourist season, an additional post at the bridge in Naryn.\"
Deputy Director of the Road Management Department under the Ministry of Transport Shabdanbek Imankulov noted that during the implementation of the project at 130-147 km of the road were installed 11 drainage pipes. The area where floods often occur refers to the fifth zone at minimal precipitation. \"For the first time so much rain falls. Experts have already prepared the conclusion that in the two places it\'s necessary to put the pipe for water dumping, and the problem will be solved. At 131-132 km \"Verkholaz\" LLC determined the amount of forced triggering of stones,\" he told to 24.kg news agency. - The project identified the most dangerous places. The Chinese company \"China Road and Bridge\" works only on it, following the task. When they paved the road, sections were not so dangerous and problem arose later, so one couldn\'t make changes to the project and put additional barriers.\"
Up the hole
Control over the execution of the project is entrusted to a group of investment projects under the Ministry of Transport. Its director Kubanychbek Mamaev asserts: everything included in the project is completed. Document was developed by Design and Research Institute \"Kyrgyzdortransproekt.\" It was this Institute to determine the areas subject to rockfalls and mudflows.
The most difficult was called segment from 130th to 147th km in Boom gorge. The problem is that the road widened to four lanes. On technical parameters it belongs to the third category, as it is clamped by the cliff to the Chu river on one side, on the other - the slope of the mountain on which the railroad passes.
Along the trails there are elevated and underground cable communications and power lines. \"Considering the difficult conditions of the area, it was decided to increase traffic capacity at the site, partly changing the parameters of the plan and profile, by increasing the width of the roadway and construction of four lanes (3.5 meters wide), which corresponds to the road of the second technical category. When designing the cross-section profile created patterns of styles of slopes and ditches pits with templates, on which intervals were prescribed. To ensure the drainage system the line profile of the ditch bottom on the left and the right was calculated, and then the bottom was modified,\" the draft of Design and Research Institute stated.
After an accident in Boom one started talking that during the construction of highway, mountain slopes were cut, drilling-and-blasting technology used. The natural landscape is broken, therefore rockfalls began. Director of the Design and Research Institute \"Kyrgyzdortransproekt\" Zhamshit Kalilov assured that there is no mistake in the project, and blasts were on other sites. Designers knew that these areas can\'t be touched, and moved the track closer to railway. \"The project was developed in 2007-2008. Until 2015 there were no problems, except the 131st km, where for the first time was a collapse in the upper part of the slope. This year, heavy rains are since March. When we made a design, the area was considered with a low rainfall. Rockfalls occurred - the effects of heavy rains,\" he said.
According to the forecast of Hydrometcenter, monthly rainfall for the area - 26 mm, but in fact for 10-15 minutes falls up to 16-20 mm. The annual rate exceeded at several times. Soil is eroded, stones became bare, there is a risk of rock falls. In September, the Issyk-Kul will host World Nomad Games, tourists and delegations will rush through the pass. Officials have assured that will provide security. The Ministry of Transport is preparing for the forced triggering of stones. However, it can\'t guarantee that landslide won\'t happen again. It should be noted that the conclusion of governmental commission doesn\'t recommend the installation of barriers. The Ministry of Transport will trigger stones at first, and will think about the construction of protecting walls the next year.