Transport Ministry reports on construction of Balykchy - Korumdu road
Transport Ministry and Road reported on the construction of Balykchy - Korumdu road, its press service reported.
According to it, in 2016 it is planned to build a section from 46.96 to 76.5 km (Tamchi airport to the post of traffic police - check in Cholpon-Ata) and from 81.1 to 83.64 km (mall area Rappoport). As of August 1 there are 235 units of equipment at sites, 574 workers. The contractor is working on the production of concrete products, involving concrete plant Balykchy. There is a reconstruction of the water line in the villages of Chok-Tal and Kara-Oi.
As reported, on the 47th kilometer of the road from July 23 started asphalting concrete pavement - the bottom layer is laid on 11 km. Excavations carried out at 17 km. The two more are underway. Underlayer of 17 km is being made. A road base is being made at 15 km. Harvested 7,000 tones of inert materials for asphalt concrete, 38 tons of materials for the base unit, 9,000 tons of bitumen.