Construction work on Bishkek – Naryn – Torugart road is scheduled to complete in December 2016
Construction work on Bishkek - Naryn - Torugart road is scheduled to complete in December 2016, the press service of the government reported.
According to it, the order for the start of construction work on the project \"Reconstruction of the road Bishkek - Naryn - Torugart, 272-365 km\" was issued in December 2013. During this time, we made certain earthworks, laid 55 km of the lower layer and 48 km - the top layer of asphalt concrete pavement, 121 culverts completed, 7 bridges built. And also produced more than 11 thousand pieces of parapets, conducted their installation on the sites.
Currently 184 units of road-building machinery and equipment involved in the construction work, also 423 people, including 30 foreigners.
The the warranty period for defects - December 2017.