Costs for reconstruction of hippodrome in Issyk-Kul grow by approximately 2.5 times

16:47, 27 June 2016, Bishkek - 24.kg news agency
Anastasia BENGARD

Costs of the reconstruction of hippodrome in Baktuu-Dolonotu village of Issyk-Kul region grew approximately 2.5 times. This was announced today at a meeting of the Parliamentary Committee on Transport.

 

Committee members noted that the original cost of the project amounted to 480 million soms, and then estimate rose to almost 1.2 billion soms. Representatives of the State Construction Committee explained that this is due to the parallel design, as well as requirement for the relevant international standards.

 

One of the deputies also noted that during the SCO summit in Tashkent, Kyrgyz President Almazbek Atambayev invited his colleagues to the 2nd  World Nomads Games, which will be held in September 2016. \"Who will be responsible if the builders don\'t meet the timeline?\" the deputy asked.

 

Representative of the State Construction Committee Almaz Abdykarov noted that their department is responsible for that.

 

According to the authorized representative of the Government in Issyk-Kul region Askat Akibaev, long-term development plan for the territory adjacent to the race track includes the construction of the hotel for 2,000 people, the congress center, sports complex, Olympic town, shopping centers and other facilities.

 

 

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18