Kumtor: scandals, dividends, investigation
The scandal around the country\'s largest Kumtor mine continues unfolding in Kyrgyzstan. 24.kg news agency is monitoring the developments and invites readers to find out what has changed in the past week.
Criminal squabbles
The office of Kumtor Gold Company in Bishkek has been searched at the end of April. The Prosecutor General\'s Office reported that it has been conducted by an interdepartmental investigative group consisting of the Prosecutor General\'s Office, the National Security Committee, Ministry of Internal Affairs and the State Service for Economic Crimes Control. The searches were carried out in the framework of the criminal case on the facts of financial violations in Kumtor Gold Company JSC, related to the illegal withdrawal of funds and assets of the company. Investigators seized all the documents relating to the case. The search took nearly four hours.
The next day, Centerra company (the Kyrgyz Republic holds 32.1 percent of the shares), whose \"daughter\" is Kumtor Gold Company (KGC), announced possible litigation with the government of Kyrgyzstan in international arbitration because of the actions of the law enforcement bodies. The company also stated about the lack of guarantees for the successful resolution of some or all of the issues on Kumtor project. In its statement Centerra emphasized that the failure to successfully resolve all issues will have a significant negative impact on future cash flows, revenues, operating results and financial position of the company.
Management is actually absent
Two days later, two Vice Presidents of Kumtor Gold Company have reportedly left Kyrgyzstan. Vice President of the company on Finance Mark Burton and Vice President on Procurement and Logistics Leslie Louw left the country on April 29.
\"The investigating authorities intend to carry out all the necessary actions with their participation. If absent for investigation activities, appropriate actions under the laws of the Kyrgyz Republic will be taken against them,\" the Prosecutor General\'s Office said.
Kumtor Gold Company itself does not associate the departure of its top managers with the criminal case. The company hastened to assure that the vice presidents have left the country for a pre-planned vacation.
Revenue falls
Developments around the largest gold deposit in Kyrgyzstan and the main asset of Centerra immediately affected the value of the company. Exactly after reports about searches in KGC office, Centerra share price fell by 10 percent and has returned to the level of $ 5.67.
Later on, the company won back its lost position. From April 29, its securities grew by 9 percent - from $ 5.2 to $ 5.67. Following the auction on May 2, 2016, share price increased by 2.31 per cent, or by $ 0.13. Therewith, Kyrgyzstan\'s stock of shares grew in price by $ 38.4 million - up to $ 438.4 million.
Meanwhile, reporters have learned that after the appeal of shareholders, the Canadian regulator - the Investment Industry Regulatory Organization of Canada (IIROC) - started an official investigation in respect of management of Centerra Gold Inc. (Centerra) and suspended trading in shares in Toronto. According to corporate law, this means that the Canadian side has expressed extreme distrust against Centerra Gold Inc. management for the events leading to the fall of the value of the corporation. Centerra itself denies the fact of the investigation.
\"On April 29, 2016, IIROC imposed a temporary suspension of trading in the security of Centerra Gold. IIROC can make a decision to impose a temporary suspension of trading in a security of a publicly listed company, usually in anticipation of a material news announcement by the company. Trading halts are issued based on the principle that all investors should have the same timely access to important company information,\" the company said in a statement.
No resolution is ahead
The conflict over the controversial deposit continued gaining momentum in Kyrgyzstan. The State Agency for Environment and Forestry Protection told reporters on May 3, 2016 that it will not issue KGC conclusion and permits for the development of Kumtor mine due to unfulfilled environmental obligations.
Notifications have been sent on April 28 (on day of searches in KGC) to the President of Centerra Gold Frank Herbert and the President of Kumtor Gold Company JSC Daniel Desjardins. The agency noted that the operator of Kumtor development does not comply with environmental protection measures, \"provided by negotiations on the restructuring of the project in 2015\".
The State Agency demands from Centerra and KGC to present the findings on pollution risk, the project on reclamation of Kumtor mine, as well as to take measures for placing and accumulation of funds for reclamation of the mine in a financial institution located in the territory of the Kyrgyz Republic, and its replenishment for the current year, to monitor the bottom deposits. In addition, the state bodies of Kyrgyzstan said that KGC has to take measures to decrease the water level in Petrov lake to avoid the risk of water mass breaking, to submit a formal response on fulfillment of the recommendations of AMEC international company and to develop a project for the formation of the waste rock dumps and limits on their placing.
The State Agency for Environment and Forestry Protection stressed that if its demands are not fulfilled, KGC will not get a positive conclusion and approval of mining plan at Kumtor. Recall, a similar situation evolved in the republic two years ago. Then the State Agency could not approve the plan of mining operations at the mine because of the intention to develop Davydov glacier. This was contrary to the provisions of the Water Code. Then the problem was decided by special government permission. The Cabinet of Ministers amended the Water Code, which allowed works near the glacier by the companies of strategic importance for the national economy. However, these amendments have not been adopted so far. Operations at the mine are conducted on the basis of the government\'s decision for the third year in a row.
Centerra does not hasten to speak out negatively against the supervisory authority. They admit that the first negative opinion on the state ecological expertise came to KGC from the State Agency for Environment and Forestry Protection in late March. At the same time, the current permits for disposal of waste and emission limit are valid until December 31, 2016 and June 30, 2016 respectively. Therefore, KGC continues coordinating plans in operation.
\"Another request for information came from the State Agency for Environment and Forestry Protection on April 28, 2016. The agency requested additional data for the prior approval of the environmental impact assessment. Kumtor Gold Company believes that the State Agency was provided all the information and documents for the issuance of the necessary permits within the framework of Kumtor project agreements and regulatory acts of the Kyrgyz Republic,\" Centerra noted.
Two months for reflection
Meanwhile, there has already been voiced a preliminary date of stoppage of works at the gold deposit - July 1, 2016. It has been determined by the State Agency for Geology and Mineral Resources of the Kyrgyz Republic. The agency has sent a notice to KGC that if the company does not pass environmental impact assessment before June 30, it will be obliged to stop production of gold from July 1, 2016.
Centerra emphasizes that it has submitted all the necessary data to the State Agency for Environment and Forestry Protection, so it does not see the reasons for the conflict. But there are no guarantees that the agency will issue a positive opinion by July 1 or later, the Canadian company said.
How will we live?
On May 3, 2016 Board of Directors of Centerra Gold Inc. has gathered for the next meeting. The meeting was held on the eve of the annual shareholders\' meeting, which is scheduled for May 17, 2016. The main topic was the events around Kumtor Gold Company JSC - the operator of the Kumtor mine, which is the biggest asset of Centerra Gold.
Information about searches in Kumtor Gold Company was unpleasant to the management of the company in Canada and raised concerns on the part of the Board of Directors. As a result, Centerra decided to actively cooperate with the Kyrgyz government and law enforcement agencies. KGC managers were tasked clearly and correctly explain their position on emerging issues in order the news of the searches not to excite the population of the republic and the company\'s partners.
Therewith, Centerra wants to completely separate the operations of the revision of the agreement on Kumtor project and law enforcement investigations. There are already some changes in KGC management structure. In particular, there was appointed a director, who is responsible for the operation of the company and the director in charge of the work with the government and government agencies. The latter, together with the lawyers, will answer all the questions that arise in law enforcement, including KGC payment of dividends to the parent company. This approach, according to Centerra, will ensure the stable operation of the mine.
No profits?
While the country watched the searches and conflicts of the state agencies with KGC, one more important detail came close to dropping out of sight. Report of the Canadian company Centerra on the results of the first quarter of 2016 has allowed noticing it. The document clearly states that all the dividends and 14.5 percent of the shares of Kyrgyzstan in the company have been arrested at the suit of the former owner of Manas Bank Valery Belokon and the Turkish company System Muhendislik on Ak-Keme hotel.
The amount of dividends of Kyrgyzstan, which are not paid to the country and are held in trust due to judicial arrest as of May 3, 2016 amount to $ 15.9 million. Legal regulations also limit the opportunities of Kyrgyzaltyn JSC in the management of 11.25 million shares, making 14.5 percent of the total stock of the Kyrgyz Republic (77.3 million shares).
There were no significant changes in the trial in the first quarter of 2016. Nearest hearings in the courts will be held in May and June 2016.
24.kg news agency continues monitoring the developments around Kumtor mine.