USD87.45EUR95.90RUB1.07
24.kg

Lame mining industry

17:47, 29 April 2016, Bishkek - 24.kg news agency
Tatyana KUDRYAVTSEVA

During the years of independence Kyrgyzstanis remembered the words that the engines of the economy are the mining and energy industry. Remembered and at the same time made clear that these industries are synonymous with problems, conflicts and decline. And their number is not reducing from year to year.

 

The long-suffering \"Altynken\"

 

A little less than a year ago Kyrgyzstan officially started production at the gold mine Taldy-Bulak Levobrezhny. There were several attempts to develop it with varying degrees of success for the last 15 years, however, but only in July 2015 it became possible to bring the matter to its logical conclusion. The license to develop the field belongs to Altynken LLC - a joint Kyrgyz-Chinese enterprise. At the same time 60 percent stake in the LLC belongs to mining corporation Zijin, and 40 percent - to Kyrgyzaltyn.

 

No such luck. Investors and government officials got excited too soon. The mine started having problems in February 2016. The workers went on strike and completely stopped production. The reason was the order of the management to reduce wages by 15 percent because of the need to save money, till the company will start working at full. Representatives of Kyrgyzaltyn, Mining and Metallurgical Trade Union and the Chinese investor were examining the conflict for two days. As a result, they managed to reach an agreement. The workers were left the former salary, but the Chinese company has replaced the head.

 

Recently, journalists have visited the company to see what the situation looks like today. Representatives of Mining and Metallurgical Trade Union met the media. They had to give the first answer about Altynken. They honestly admitted that the conflict is settled. However, the main issue - increase in wages - remains open. The tension also remains. And the plant\'s management understands it.

 

\"Now everything is quiet. But there always will be those who are dissatisfied with something. Try to do some work for eight hours at mine and see what you will feel. We try to explain that, as soon as the plant will get its first profit, it will be better. In the meantime, one needs to wait a bit,\" the first deputy director of Altynken LLC Umar Izabaev says.

 

The plant will be able to receive the first income only after the launch of gold recovery plant. This point is postponed each time. The equipment has undergone a 72-hour test, however, leak in the flotation tailings pond has been revealed. The launch was postponed again. It was decided to replace the membrane completely. Now the Management voices possible launch date - May 20.

 

\"If there are bad weather conditions, the launch may be postponed again. But this is an objective reason. In addition, we had to change the project. Initially it was assumed that Altynken will produce only gold bullions. However, tests have shown that the ore has a high content of copper. We can\'t just throw it. Therefore it was decided that the plant will produce a copper-gold concentrate,\" safety engineer of the gold recovery plant enterprise Kadyrbek Abdybachaev said.

 

By the way, the extraction of ore in the mine is in full swing. At present, there are about 200,000 tons of ore. That\'s enough for about five months of work of the gold recovery plant.

 

Uranium trail

 

If the workers of Altynken demand to raise their salaries, the employees of Kara-Balta mining plant can\'t even count on that. In late February the plant was stopped completely. People were sent on holidays without pay with keeping 2/3 of the salary. However, enterprises have enough finances for 3-4 months of downtime in the best case. Half of the term has already passed, but the situation hasn\'t changed.

 

\"There is really complex economic problem. But another question - attitude of the employer to the employees. Employer there is Russian. The company is part of \"Renova\" structure. This is a major Russian holding company, which is headed by the oligarch Viktor Vekselberg. He is famous for purchase of Faberge eggs at auction and their return to Russia. So, the company uses the subsoil not only of Russia, but also of many countries of the world. And when it becomes unprofitable, they simply throw the company as it is now in Kara-Balta. No one talks with people. The plant is town-forming, when it was bought in 2008 one understood it, took responsibility. It is necessary to communicate with people, to devote to the plans, they can tell where the way out is. But there is no dialogue. The question whether the plant will work is not just curiosity for the people,\" the coordinator of the Center for Social and Labor Rights Eduard Vakhmin says.

 

The chairman of Central Committee of the Mining and Metallurgical Trade Union Eldar Tadzhibaev agreed with him. The union, recall, persuaded employees of the plant not to hold a rally in February. But problems remain. Within two months the case didn\'t make a progress.

 

\"We are negotiating with management, watch over the latest developments. There are several solutions to the problem. For example, if som exchange rate falls, import of iranium for processing will become easier. On the other hand, Kazakhstan protects its producers and primarily sells raw materials to them. There is another option - business process re-engineering. Also the issue of return of the company to the state is being discussed. Perhaps \"Renova\" just will sell the plant,\" Eldar Tadzhibaev commented.

 

Whatever it was, solving of the problem takes time. No one can predict how long it will take to give a second life to the mill. Consequently, Kara-Balta mining plant joins a list of problems of mining enterprises. Who is to blame - the investor or the state - is a rhetorical question.

 

Kumtor of our discontent

 

The flagship of the mining industry of Kyrgyzstan - Kumtor mine. It is also a major headache of the Government and the source of political bargaining for the deputies. For the second year in a row, the company operates thanks to the special decision of the government. The question of amending the Water Code, which gives the right for the activity near the glacier to the strategically important for the country  production, hasn\'t been decided yet.

 

Not one of the Kyrgyz Prime Ministers fell at Kumtor. The previous Prime Minister Temir Sariyev had formed a special commission, which studied the effect of the work at the mine on Davydov and Lysyi glaciers. The Commission has decided that there is no direct impact. Glaciers would still melt. The deputies heard the information, but didn\'t make the final decision on the amendments to the Water Code. They plan to return to it in the middle of May, after a visit to the enterprise.

 

Meanwhile, the next Prime Minister Temir Sariyev left post. He was replaced by Sooronbay Jeenbekov. Prime Minister has criticized some decisions of his predecessor, some even canceled. Is it possible to hope for solidarity in the issue of Kumtor in this situation? Unknown. As it is unclear whether someone will put an end to the issue of Kumtor.

 

If we take into account the smaller fields in the country, then there are regular problems with them. After the sale of the controversial coal deposit Bel-Alma, residents haven\'t stopped holding rallies against the developers. Every spring and autumn permanent residents oppose the development of the second gold reserves- Jerooy field.

 

And this year the government, meanwhile, is planning to put up brown coal deposit Kara-Keche for investment competition. It seems that the mining industry will have more problems soon.

 

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18