One of failed Toktogul HPP hydropower units put into operation

13:11, 15 January 2016, Bishkek - 24.kg news agency
Anastasia BENGARD

One of the failed hydropower units of Toktogul HPP was put into operation. Press service of Electric Stations JSC informed 24.kg news agency.

 

The company reminded that two of the four hydropower units have failed. One of them has been repaired, and the second is still under repair.

 

The day before, unit transformer T-2 of Toktogul hydroelectric power station was taken out of the repair and put under tension at about 5.20 p.m.

 

 Recall, emergency shutdown of a block transformer of the second hydraulic unit occurred on December 23 at Toktogul HPP.

 

 Earlier on, the Prime Minister stated that transformer №2 will be repaired by January 15, and restoration of the cables, which failed on December 28, will take about two months.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18