Aibek Kaliev: There is three generation-shedding in Toktogul HPP

17:03, 29 December 2015, Bishkek - 24.kg news agency
Suyunbek SHAMSHIEV

\"Yesterday at 6.58 three generators - the 1st, 3rd and 4th at Toktogul HPP were disconnected because of oil leakage in cables,\" Deputy Minister of Economy of the KR Aibek Kaliev said at a press conference.

 

According to him, the cables at the Toktogul HPP were installed 40 years ago and are used till today, although such cables are not produced anymore.

 

\" Electricity supply is limited at the level of 235 megawatt-hours in Chui, Issyk-Kul, Naryn, Osh, Jalal-Abad regions and Bishkek,\" the official said.

 

According to him,  the restrictions have been lifted today from 12.00 p.m.. \"Now Russian specialists are working on elimination of the breakdown,\" Aibek Kaliev said.

 

He said that the repair can last 2-3 weeks and probably 6 million kilowatt hours of electricity will be imported.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18