“Makmalzoloto” Enterprise resumes work after six months of idle
Departments of Makmalzoloto enterprise resumed work after six months of idle, Kyrgyzaltyn JSC reported.
According to it, yesterday was held the launch of new tailing dump with volume of 2,600 cubic meters and with service life of 12 years. Today about 30,000 tons of ore accumulated. This volume is sufficient for the smooth operation of the company till April 2016.
\"Construction of the tailing dump was planned back in 2009, but completed only now. In general, 325 million soms were spent on the project. The need to launch new tailing dump arisen because of the filling of the old one,\" the press service of Kyrgyzaltyn says.