About 3mln soms allocated for construction of Cholpon high-voltage substation
About 3 million soms were allocated for construction of 35/10 kV high-voltage substation in Cholpon village, Issyk-Ata district of Chui region, press service of Severelectro JSC reported.
According to it, the works are nearing completion. \"This significantly reduces the length of overhead 10 kV transmission line from Ivanovka substation, allows faster serving of the power lines and as a consequence, increases the reliability of power supply of Gidrostroitel, Ken-Bulun, Cholpon, Dostuk villages. At the time, the length of the longest feeder line from Ivanovka substation is 23 kilometers,\" the press service says.
It is noted that at the end of September 2015, the company put into operation a new 35/10 kV high-voltage substation Bakair in Talas region.