Second phase of Toktogul HPP reconstruction costs $ 450 million
The second phase of reconstruction of Toktogul hydropower plant will cost $ 450 million. This was announced yesterday at presentation of the project.++
It was noted that two banks -Eurasian and Asian- will finance the construction. The main part of the required amount (about $ 350 million) is allocated by the Asian Development Bank. The Eurasian Development Bank will only subsidize the purchase of equipment for the second and the fourth units of Toktogul HHP ($ 100 million). Allocated by the banks money is grant and a concessional loan.
\"The second phase of reconstruction of Toktogul HHP consists of three projects. The first is the reconstruction itself and replacement of equipment at the plant. In addition, there will be developed feasibility study for construction of Uch-Kurgan HPP. We also plan to make an assessment of the whole complex of HHP assets to attract investments for further modernization in future,\" the Vice Prime Minister of Kyrgyzstan Valery Dil said at the presentation.