Kyrgyzstan needs $200 mln for implementation of CASA-1000 project
Kyrgyzstan needs $200 million for implementation of the CASA-1000 project. The Director General of National Electric Network of Kyrgyzstan JSC Medetbek Aitkulov states at opening of Datka-Kemin PTL.
\"Construction of power transmission line from Datka substation in Tajikistan is provided within this project. A substation of 500 kW capacity is located in the territory of the country, we will connect it to Datka substation. Through these lines we will be able to export electricity to Pakistan, Afghanistan,\" Medetbek Aitkulov notes.
\"The following donors - the World Bank, the Islamic Development Bank and the European Development Bank are identified with regard to funding. Interest of concessional loans is different. Duration of the project will amount to about 3 years,\" he said.