Bishkek HPP receives machinery and equipment at $3.1 mln for its modernization

16:36, 15 May 2015, Bishkek - 24.kg news agency
Tatyana KUDRYAVTSEVA

Bishkek Hydro Power Plant received machinery and equipment at $3.1 million for its modernization, the executive director of the group on modernization management Temirlan Brimkulov told reporters today.

 

According to him, it received two transformers and accessories worth $8,233 million. The dismantling of turbine and boiler №1, turbine unit №2 began since May 12.

 

\"All the works are on schedule. The installation of the first unit is scheduled to complete by July 2017, the second - in August 2017. In addition, the Chinese party establishes additional transformers at its own cost,\" Temirlan Brimkulov said.

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18