Additional $15.1 mln to be allocated for reconstruction of Bishkek – Naryn – Torugart road
Additional $15.1 million will be allocated for the reconstruction of Bishkek - Naryn -
Torugart road. The Parliamentary Committee on Budget and Finance today approved a corresponding agreement between the Kyrgyz Republic and the Asian Development Bank (ADB).
It is noted that the question of the financing of the project \"CAREC Transport Corridor 1\", the road Bishkek - Torugart. For the rehabilitation of the site from 479th to 539th kilometer the ADB has allocated $55 million. Construction work began in 2013.
\"Additional work relating mainly to increase the height of the embankment subgrade and improve the drainage system. This will reduce the risk of cracking in the asphalt concrete pavement during frosts. The loan amount is $10.8 million grant - $4.3 million. Kyrgyzstan has received a loan for 32 years under 1.5 percent per annum with a grace period of 8 years. In this case, the government\'s contribution will be $2.9 million,\" the Ministry of Transport noted.