Construction of new high-voltage substation in Bishkek is almost completed
Construction of new high-voltage substation in Bishkek is almost completed, Severelektro OJSC reported.
It is noted that \"Izdatelstvo\" substation is located at the intersection of Leo Tolstoy and Sultan Ibraimov Streets. In addition to the two power transformers of 6,300 kVA, another transformer of the same capacity is installed.
\"A third turn of all high-voltage \"Izdatelstvo\" substation is to remove the problem of overloading the \"Central-4\" substation and ensure the reliability of power supply area bounded by Suyumbaeva and Yusup Abdrakhmanov streets, Chui Avenue and the railroad,\" the company noted.