Warranty period operation starts at Datka substation

20:00, 30 September 2014, Bishkek - 24.kg news agency
Julia KOSTENKO

Warranty period operation starts at Datka substation. \"National Grid of the KR\" OJSC reports.

It is noted that construction works at 500 kWh substation are fully completed. About123.3 kilometers of wires (out of 405 kilometers) are pulled and roads are laid on the route of Datka - Kemin power line to 926 pylons.

About 1,539 people are working at construction bases, 103 of them - local experts. Construction sites involve 338 units of machinery and special vehicles.

Recall, construction of \"Datca - Kemin\" line and \"Kemin\" substation will ensure energy security of Kyrgyzstan in future. In 2015 the construction of 500 kWh transmission line will finish.


CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18