Yan Atkinson: Restructuring of Kumtor project – a complex process, but we are working hard on its completion
The President of \"Centerra Gold Inc.\" Ian Atkinson tells in an interview about the progress of negotiations on restructuring of Kumtor project, possible terms of creating on a deposit a joint venture with Kyrgyzstan, as well as about the work of the mine in 2014.
-\"Centerra\" and \"Kumtor Gold Company\" summed up results of the activity of the largest gold mine in Kyrgyzstan for the first half of 2014. What are they?
- It is quite successful. In general, for six months 180,793 ounces, or 5 tonnes and 623 kilograms of gold were produced at Kumtor mine. The company transferred to the budget of Kyrgyzstan more than $58 million in taxes and mandatory payments.
According to our preliminary estimates, the volume of production at Kumtor gold mine in 2014 will amount to 550-600,000 ounces, or 17.1-18.7 tonnes of gold. At the same time, as in 2013, more than half of the total volume will be produced in the last quarter of 2014, when we reach the land plot with a high content of gold in SB area of Central open pit.
Total capital expenditures in 2014 (except for capitalization of stripping operations) are planned in the amount of $86 million, $43 million of which will be spent for development, and the remaining $43 million - for modernization of fixed assets.
Now the volume of production at Kumtor gold mine is not very high, because Centerra invests in the project a significant amount. It will continue to do it unless we reach the area containing ore with a high content of gold in SB zone.
-In January Kyrgyzstan and Centerra Gold Inc. signed an agreement on terms of the restructuring. However, the work wasn\'t completed. How would you assess the current state of negotiations?
- \"Centerra\" has been and remains to adhere to the task of completing the restructuring in full compliance with the agreement. The Board of Directors of the company has always taken the view that any agreement must be equally fair to all shareholders of Centerra, including OJSC \"Kyrgyzaltyn.\" Restructuring must be approved by the shareholders of our no Kyrgyz shareholders (their share in Centerra amounts to 67 percent), and if the restructuring is unjust, it won\'t be accepted.
We hope that our shareholders will support it. Therefore, together with our consultants on legal and financial issues we have been preparing the whole package of relevant documents. In June of this year Centerra sent the document to the Prime Minister of the Kyrgyz Republic and the working group on Kumtor, as well as external consultants of the Kyrgyz government - DLAPiper and Pricewaterhouse Coopers companies.
We have not received a complete answer to the draft agreement, but we hope that the working group will submit the detailed comments in the near future. In addition, we have prepared another 9 major agreements. Centerra is ready to vigorous and constructive cooperation with the working group and its professional advisors for an early conclusion of the arrangements stipulated in the agreement on the terms of restructuring. Once agreements are signed, they will be submitted to the Parliament and shareholders of Centerra and then they will be sent to the Court of Canada for approval.
In addition, these agreements must undergo an independent examination on the issue of fairness to all shareholders. This is a complicated process, but Centerra makes every effort to complete the restructuring for the benefit of all shareholders, including OJSC Kyrgyzaltyn.
- You said that the restructuring depends on whether it will receive the approval of shareholders. Who, besides Kyrgyzaltyn, is one of the shareholders of Centerra? And whether they will approve the transaction contemplated by the agreement?
- First of all I would like to repeat: we hope that the restructuring will be approved by shareholders.
They include a number of the world\'s largest financial institutions, the headquarters of which are located in New York, London and other European countries. These investors - the organizations are far from simple. They can choose where to invest money. They run to billions of dollars.
As I said, our agreement requires the approval of our international investors. That is why it is important to prove that the agreement is valid and deserves their support.
- How do you continue to negotiate with the government of Kyrgyzstan?
- As a result of actions, made by the General Prosecutor\'s Office, representatives of Centerra could not come to Bishkek for direct negotiations. We cooperated with the Prosecutor General\'s Office to resolve all issues and problems in connection with Kumtor, hoping for a speedy completion of the investigation. However, Centerra, without waiting for its end, proposed to hold a meeting outside of Kyrgyzstan, for example in Istanbul. We have not yet received any response yet. When we get confirmation about the completion of investigation from the General Prosecutor\'s Office, we look forward to resumption of meetings in the Kyrgyz Republic.
All the while we couldn\'t come to Bishkek for personal participation in the negotiations, but we continued to work by phone and through our professional advisers. It seems to us that we have made significant progress on a number of issues, including the list of agreements to be signed as part of restructuring.
- The development of Kumtor gold mine is very important for the economy of the country. How to speed up the negotiations and establishment of a joint venture, the format of which is beneficial for the Kyrgyz side?
- For the early completion of the restructuring and adoption of a final decision, it is quite essential for the Kyrgyz Government to attract highly qualified local and international consultants the Government of the Kyrgyz Republic. This is necessary in order to avoid debates around Kumtor project in the future. The faster the restructuring is completed, the sooner the country will be able to take full advantage of direct participation in the project in a joint venture. Of course, receiving proportionate share of the direct cash flows from the development of the field is among the main and immediate benefits.
In addition, the completion of restructuring will become a positive signal to other major foreign investors - signal of the openness of Kyrgyzstan for business development.