Chinese company makes duplicate of stolen parts for construction of power transmission supporting lines Datka - Kemin
Chinese company made a duplicate of stolen parts for the construction of power transmission supporting lines Datka - Kemin, the National Grid of Kyrgyzstan OJSC said to 24.kg news agency.
It is noted that today power engineers plan to complete the construction work, in the result of which Dzhumgal district of Naryn oblast stayed without electricity from August 5.
Equipment designed for supporting lines is not found. A duplicate was ordered in factory in China. Contractor - TBEA -made it at its own expense. The National Grid of Kyrgyzstan assured that it won\'t affect the final cost of the project. Amount of damage is 71,300 soms.
Recall, it was planned to restrict the flow of electricity to consumers of Dzhumgal and Kochkor districts in connection with the installation work till August 12. However, because of the disappearance of the components the works were extended. Construction of the line Datka - Kemin and Kemin substation in the future will ensure energy security of Kyrgyzstan. Construction of 500 kV transmission line will be completed in 2015.