How rich energy.kg pretends to be poor

18:15, 22 July 2014, Bishkek - 24.kg news agency
Julia KOSTENKO

The energy sector of Kyrgyzstan develops only through borrowings. There is no own money to build new power plants and transmission lines, especially when it comes to large, multi-year construction projects. As practice shows, it is more profitable to borrow at high interest rates, because the money is spent irrationally and more than half ends up in the \"gray\" schemes or evaporates into the air kilowatts.

 

From holding to shareholders

 

When the government of Kyrgyzstan decided to dissolve Kyrgyzenergo OJSC, its loans were distributed among established companies. Most of all, namely, $70,903,227.6, fell on the shoulders of National Grid of the KR. More than $20 million went to Electric Stations OJSC, $15.8 million - Bishkekteploset OJSC. At that time, total loans and loans of the energy sector was $112,180,435.54.

 

But new facilities and renovate old needed more money and which also were borrowed. By 2013 Electric Stations took another 9 billion 154,228.4 million soms and about $125 million that went into the construction of Kambarata-2, emergency aid for the purchase of oil and technology, as well as the successful completion of the heating season 2008-2009 when the water level in the Toktogul reservoir dropped to a critical level, and there were rolling blackouts in the country.

 

It should be noted that the accrued fines company owns 95,354.3 million soms. Principal debt resulted from the use of funds to finance the construction of Kambarata-2, amounting to 6 billion 261,722.1 million soms, or 68 percent of the total debt.

 

Small HPP for big problems

 

Originally Kambarata-2 hydro power plant (HPP) was planned to be launched on the Day of Energy in 2009. For these needs 5 billion soms were allocated by the government. But then something went wrong, and the terms were moved, of course, bloating the budget.

 

The Accounting Chamber auditors found that the construction of the station had significant changes in the direction of increasing performance both in terms of funding and for the development of credit. In fact, on the first unit 8 billion 678.5 million soms were spent, including 50 percent of the funds allocated by the Russian party.

 

The greatest financial irregularities were discovered during a large-scale explosion to create a Kambar-Ata-2dam on the Naryn River. For its construction consumed 681.2 million soms, but most of them were just wasted. Explosive should have been made from three components, but in order to save one component was replaced by another and excluded from the composition. But later it was found out that the breed didn\'t lay down where it is needed, and it had to be moved by bulldozers.

 

In addition, power engineers estimated the overall cost of metalwork imported during the Soviet time, inflating its cost up to 336,481.6 million soms. Significant funds were spent to purchase and transport of cement. ShumkarTransGrupp LLC transported over 50,000 tons of cement totaling 119,469 million soms from April 2008 to May 2010. Transporting one ton from the factory to the construction site is 2,388 soms. Accounting Chamber auditors detected excess of current prices on the pricelist at 64,408.7 million soms.

 

Similar facts of unreasonably high costs for freight were in Gidroenergostroy OJSC on 794,000 soms, Kyrgyzgidrospecstroy - 1.5 million, Ala-Archa JSC - 6.3 million.

 

According to the results of the audit during Kambarata-2 construction infringements by 1 billion 342,165.8 million soms were revealed.

 

Generous TBEA

 

At the moment the Major project conducted by NESK (Independent Power Company) is construction of substations and 500 kV transmission line Datka - Kemin which is financed by the Chinese company TBEA.

 

About $208 million for the construction of Datka and reconstruction of 220 kV electric networks in southern Kyrgyzstan were allocated. The agreement passed all internal procedures, the ratification in the Parliament. However, no one was confused that the contractor is defined without a tender. The KR agreed to give the project to the one imposed in China.

 

The project is not yet fully implemented, but significant shortcomings are revealed. By contractual agreement the contractor should deliver to NESK equipment for $104.8 million. However, its value has reached $107.6 million.

 

The Accounting Chamber sent a request to TBEA, and received the answer that additionally supplied equipment and materials in excess of the contract price are produced by a Chinese company for its own account and transferred to the Kyrgyz party in the form of grants.

 

Nice to have an extra assistance to Kyrgyzstan, especially gratuitous. However, keep in mind that the resulting asset should be recognized as income of NESK at $2.7 million, and shareholders put dividends to this amount.

 

By the way, note that TBEA performs as contractor of Bishkek TPP reconstruction, which is estimated at $386 million. In addition, the contractor is safe and has provided a grant of $20.3 million for the purchase of equipment, furniture and construction of schools. The project is being developed now, and the deputies, who took the final decision, have doubt of the executer but they don\'t have enough courage to rescind its decision, and the amount of the loan is too big to voluntarily give up the money.

 

Economical distributing company

 

Distributing companies take debts willingly, but modest in comparison with Electric Stations and NESK. In total, they have 1 billion 516,301.3 million soms. Of course, most of the debt has Severelectro serving Bishkek and Chui province.

 

In 2011, the distributing companies have received credit for 20 years. Vostokelektro OJSC allocated $303,100, Oshelectro - $5.2 million, Severelectro - $385,100, Jalal-Abadelektro - $3.7 million. However, none of them use the money effectively.

 

Buying concrete supports, the tender commission of Vostokelektro opted the provider who has no qualification reputation in the market. ArekhSom LLC supplied 300 supports at 4,199.7 million soms. Goods didn\'t conform to GOST quality characteristics and specifications and wasn\'t fit for use. Supplier didn\'t admit that supports were of poor quality, and refused to pay damages.

 

Now law enforcement bodies have to reveal violations and try to recover the funds that energy inefficiently spent.

 

I love money

 

Leadership of the Ministry of Energy and Industry, energy companies every day complains about the lack of funds and the current deficit. The public is trying to be convinced that the industry is in a cornered position, especially now, when the rich energy Kyrgyzstan forced to buy electricity from neighboring Tajikistan, because a few years ago wanted to get excess profit energy and exported more energy than it should, of course, having used the water in Toktogul reservoir. Now there is no money not only for repair, but also for the purchasing of fuel for power stations in Bishkek and Osh. Again industrialists want to find investors, or to use a leaky state treasury in order to get credit or a loan.

 

According to the auditors, the Ministry of Energy doesn\'t check the use of credits, there is no policy of financial management. They don\'t hurry up to develop legislatively approved regulations, providing the control feasibility and reliability of the write-off of fuel for heating plants. Energy Minister Osmonbek Artykbayev insists that industry deficit is 6.7 billion soms. However, he didn\'t count how much money was wasted, and who will be responsible for it. Lamentable that at the time of payments on current loans no power engineer will no longer be in the system and those even who don\'t know about the existence of debts will have to pay for it.

 

 

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18