In Kyrgyzstan 334 km of power transmission lines repaired
In Kyrgyzstan 513 kilometers of power lines out of 334 repaired. The Deputy General Director of JSC \"National Grid of the KR\" Aleksey Borodin sated today at a press conference.
According to him, since the beginning of 2014 20 high-voltage transmission lines with a total length 334.5 kilometers are renovated. About 100, 311.1 soms were spent on the repair campaign. \"Last year, the absolute maximum was reached in February 3000 and reached 135 MW. We had a lot of problems, power lines and Frunze substation operated with overloading,\" Aleksey Borodin said and added that soon repairs of transformers will start.
\"By winter we\'ll prepare the equipment, which can carry a maximum load,\" he said.