Erkin Abdykalykov: Reconstruction on heat networks is completed, hot water to be resumed on June 19

14:41, 16 June 2014, Bishkek - 24.kg news agency
Julia KOSTENKO

\"Reconstruction on the heat networks is completed, hot water will be resumed on June 19,\" the director General of Bishkekteploset OJSC Erkin Abdykalykov said to 24.kg news agency.

 

According to him, all the planned works are 100 percent completed. \"On the weekend, the system was filled with cold water. While no leakage is established. Today hydraulic tests will begin, during which arisen problems will be fixed. As promised, hot water will be resumed from June 19,\" Erkin Abdykalykov said.

 

It should be noted that every year hot water is cut off for a month for reconstruction. It\'s impossible to cut it off in several districts for several days because of technical device networks.

 

 

CONTACTS

SOCIAL MEDIA

TelegramYouTubeWhatsAppFacebookInstagram

© News Agency «24.kg» - News of Kyrgyzstan. All rights reserved. All information posted on this website is intended for personal use only and may not be distributed without the written permission of NA «24.kg». The editorial team is not responsible for the content of reprinted materials and statements of individuals. +18